| One vertical
panel has been installed. |
In the same amount
of time, SnapCabs are completed with pad hooks and hand
railing installed. |
|
| Reveals: |
Five reveal strips to install between
each panel |
Reveals: |
Two reveal strips to be installed (corners
only) |
|
| Measuring: |
With the aide of a plywood clip jig,
six z-clips are precisely mounted for each hanging panel.
For this job, there would be a total of 24 clips installed
using 48 screws. |
Measuring: |
With the SnapCab system, you only
have to center and level the first layer. the rest of
the wall registers itself automatically. Instaled with
25 screws. |
|
| Toe Kick: |
Must be installed prior to reveal strips
and panel. |
Toe Kick: |
Pre-installed on first layer of ILP panel
system |
|
| Hand Railing: |
After all four vertical panels are installed,
measurements must be taken to lay out location of the
hand rail hardware. Drill and bolt hand railing standoffs
through the wall of the cab, and nut the bolts from outside
of the cab. |
Hand Railing: |
Pre-installed on panel. |
|
| Pad Hooks: |
After all four vertical panels are installed,
measurements must be taken to layout location of the pad
hooks. Drill and bold pad hooks through the wall of the
cab and nut the bolts from outside the cab. |
Pad Hooks: |